Provide synthetic turf and improvements to the Baseball and Softball fields. Place refurbished bleachers at Baseball and Softball fields. Resurface the Cardon Field track and replace the long jump and pole vault runways. Resurface the tennis courts and place refurbished bleachers. Replace the gravel area with grass and sidewalk access. Construct a new indoor practice facility.

At Doc Harris Stadium, increase the movable bleacher seating and improve safety by providing stair access. Add power and improve the sound system.

At Skyridge Middle School, replace the two long jump runways and restripe the track.

Budget
Funding Source
Project Status
Architect
Contractor
Estimated Start
Estimated Completion
$5,000,000
2016 Bond
Design
Robertson Engineering
Various
Various: Spring 2018, 2019, 2020
Various: Fall 2018 & 2019, Winter 2020