The District secured a contract with an Energy Services Company (ESCO) under the Department of Enterprise Services to provide retro-commissioning and HVAC improvements to the following schools: Dorothy Fox Elementary, Prune Hill Elementary, Liberty Middle, Skyridge Middle, Hayes Freedom High, and Camas High schools; upgrade to LED lighting in parking lots at the Zellerbach Administration Center, Doc Harris Stadium and Camas High School; upgrade to LED interior lighting at Dorothy Fox Elementary; replace the bus wash facility; and add ventilation to the CHS art room. This project takes advantage of energy grants and energy incentives.
Budget
Funding Source
Project Status
Architect
Contractor
Estimated Completion
Estimated Completion
$2,343,000
2016 Bond & Grants
Construction
WillDan/Abacus ESCO
Various under ESCO
July 2017
September 2018
2016 Bond & Grants
Construction
WillDan/Abacus ESCO
Various under ESCO
July 2017
September 2018